    摘要:

    为解决矿山法隧道利用盾构空推进行二次衬砌的技术难题,以深圳某地铁隧道区间工程为例,通过方案优化,合理设定导台的高程,选择合适的管片与导台间空隙的支撑材料,采取对成型管片持续的测量监测,使用混凝土对管片与矿山法隧道壁之间空袭进行充填,设定合适的盾构推进参数等方法,成功的解决了矿山法隧道利用盾构空推实施二次衬砌的技术难题,以期为今后类似工程施工提供借鉴。

    Abstract:

    In order to solve the technical problem of secondary lining of mine tunnels using shield air thrusters, taking a subway tunnel section project in Shenzhen as an example, through scheme optimization, reasonably setting the elevation of the guide platform, selecting the supporting material for the gap between the segment and the guide platform, adopting continuous measurement and monitoring of the formed pipe segment, using concrete to fill the air attack between the pipe segment and the tunnel wall of the mine method, and setting appropriate shield propulsion parameters, etc., the technical problem of secondary lining of the mine tunnel using shield air thruster was successfully solved. In order to provide reference for similar engineering construction in the future.

    参考文献
    相似文献
    引证文献
引用本文
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2023-09-17
  • 最后修改日期:2023-09-17
  • 录用日期:2023-11-06
  • 在线发布日期:
  • 出版日期: