基于多源数据关联的邻轨深基坑施工造价偏差溯源与监理审核方法
DOI:
CSTR:
作者:
作者单位:

1.广州铁路职业技术学院;2.广东省轨道交通地质灾害智能监测工程技术研究中心;3.上海建工集团股份有限公司

作者简介:

通讯作者:

中图分类号:

基金项目:

广东省普通高校自然科学类重点领域项目(2025ZDZX4158);广州市现代产业学院培育项目(2025XDCYXY004);广州铁路职业技术学院揭榜挂帅项目(GTXYGS250101);广州铁路职业技术学院重点项目(GTXYZD250201)


A Traceability and Supervision Review Method for Construction Cost Deviation of Deep Foundation Pits Adjacent to Operating Rail Transit Based on Multi-source Data Correlation
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    邻近运营地铁的深基坑施工中,工程量、进度、部位和变更凭证分散于不同台账,监理难以区分已授权的费用调整与施工履约超支。为此,提出面向监理计量与支付审核的造价偏差溯源方法:以WBS—CBS—空间—时间—凭证五维编码归集成本;设置挣值基准与授权目标,分别计算成本暴露率和履约偏差率,并以区间偏差率检验纠偏效果;按科目贡献、时空筛选和因素分解三级穿透定位偏差,经凭证复核后形成可支付、待变更、需核减、待补证四类审核状态。参数化情景演算表明,支护工程复核范围可缩小至9 d施工窗口;纠偏后区间偏差率为0.50%~1.30%,而累计履约偏差率仍为0.71%~3.41%,判断纠偏效果宜以区间指标为主。

    Abstract:

    In the construction of deep foundation pits adjacent to operating metro lines, engineering quantities, schedules, construction locations and change vouchers are scattered in different ledgers, making it difficult for supervisors to distinguish authorized cost adjustments from performance-related overspending. This paper proposes a cost deviation traceability method for supervision measurement and payment review. Costs are aggregated using five-dimensional coding of WBS–CBS, space, time and vouchers. The earned value baseline and authorization targets are set to calculate the cost exposure rate and performance deviation rate, and the interval deviation rate is used to test correction effectiveness. Deviations are located through three-level penetration analysis of subject contribution, spatio-temporal filtering and factor decomposition. Following voucher verification, four review statuses are formed: payable, pending change, to-be-reduced and pending supplementary document. Parametric scenario simulations show that the review scope of retaining works can be limited to a 9-day construction window. After correction, the interval deviation rate is 0.50%–1.30%, whereas the cumulative performance deviation rate stays at 0.71%–3.41%. Accordingly, interval indicators should be adopted as the main criterion for evaluating correction effects.

    参考文献
    相似文献
    引证文献
引用本文
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2026-10-17
  • 最后修改日期:2026-10-17
  • 录用日期:2026-11-18
  • 在线发布日期:
  • 出版日期:
文章二维码