Abstract:In the construction of deep foundation pits adjacent to operating metro lines, engineering quantities, schedules, construction locations and change vouchers are scattered in different ledgers, making it difficult for supervisors to distinguish authorized cost adjustments from performance-related overspending. This paper proposes a cost deviation traceability method for supervision measurement and payment review. Costs are aggregated using five-dimensional coding of WBS–CBS, space, time and vouchers. The earned value baseline and authorization targets are set to calculate the cost exposure rate and performance deviation rate, and the interval deviation rate is used to test correction effectiveness. Deviations are located through three-level penetration analysis of subject contribution, spatio-temporal filtering and factor decomposition. Following voucher verification, four review statuses are formed: payable, pending change, to-be-reduced and pending supplementary document. Parametric scenario simulations show that the review scope of retaining works can be limited to a 9-day construction window. After correction, the interval deviation rate is 0.50%–1.30%, whereas the cumulative performance deviation rate stays at 0.71%–3.41%. Accordingly, interval indicators should be adopted as the main criterion for evaluating correction effects.